DripDrop USA Project Progress reports

August 31st, 2023 Update: Water Flowing from the 6 panels that we have connected.  Engineers are working to gathering all the data over next week.

August 3rd, 2023 Update: We will connect a total of 768 panels. Water production is 1.8 gallons per panel an hour. That is a total of 1,382 gallons per hour and 33,177 gallons per day.

Project Update – May 16, 2023:

We have a production process capable of manufacturing significant, fully functional parts!

Below is a link to a video of the production cycle on the thermoforming machine.  The parts are loaded directly from the thermoforming machine onto a table to rough trimmed by an operator and are allowed to cool under some weight to maintain their shape.  Parts are then loaded onto a fixture and are CNC trimmed, a 1/2″ plastic barb fitting is installed and parts are leak tested prior to packing.

https://clipchamp.com/watch/xSmkxJGeDAu

The Process is reliable, repeatable, and automated on the forming side.  Cycle time is currently at about 6 minutes, with a target of 5 minutes or less for the pilot run.  Currently, we have a reasonable procedure to install and seal the burb fitting which will do in the short term.  However, we are still developing a production-worthy solution which will be a one-part fitting and seal to be installed with minimum labor.

Material thickness was reduced from the initial combined thickness of 0.200″ to 0.160″ in the latest run which is a 20% reduction.

Attached also is a video of a test performed to show parts are sealed and water flow from the input to the output and a couple of images.

C&K will notify the final quantity count and provide shipping information once the parts are packed and ready to go.

Best Regards,

– Jesse D/D/USA

Panels are being manufactured for delivery soon.  See panel images below.  We will provide additional progress reports and upload additional images soon.

Please reload this page if you did not see the images below: